Construction glossary

What are Indirect Costs?

Indirect costs, in the context of the construction industry, are expenses not directly tied to a specific project, but are essential for the overall operation of a construction firm. They represent the expenditures that do not contribute to the building process directly, yet they are crucial for the smooth running of projects. Such costs could include administrative expenses like office rent, utilities, and salaries of personnel not active on the field but are involved in management, planning, or supervision. Other examples include insurance, security, equipment depreciation, and legal fees. Understanding indirect costs is key to accurate budgeting and financial control in construction projects. Failure to consider these costs can lead to a significant underestimation of the actual project cost, leading to financial losses. Therefore, contractors need to accurately factor indirect costs into their pricing to secure profitability.

Trusted by trade contractors across the country

Other construction terms

Conditional

What is Conditional?

In the construction industry, the term "conditional" typically refers to a state or situation where certain obligations, requirements, or criteria must be met for a particular outcome or transaction to occur. This term is often used in contracts or agreements. For instance, a construction project could be conditional upon gaining necessary building permits or approvals, meeting safety standards, or obtaining adequate funding. The failure to fulfill these conditions could suspend or terminate the project.

Financial Statements

What are Financial Statements?

Financial Statements, in the context of the construction industry, are formal records that portray the financial activities and conditions of a construction company. They're crucial for presenting a company's financial health to stakeholders and assisting in making strategic decisions. The primary types include balance sheets, income statements, cash flow statements, and equity statements. The balance sheet gives an overview of the company's assets, liabilities, and shareholders' equity. The income statement shows revenue and expenses, revealing the profit or loss over a period. Cash flow statements illustrate how changes in balance sheet and income statement items affect cash and cash equivalents. Equity statement depicts changes in the owner's interest in company during the accounting period. Without these statements, it would be challenging to understand a construction firm's economic status and make informed future financial decisions.

Billings in Excess of Costs

What is Billings in Excess of Costs?

Billings in excess of costs (also called overbillings) occur when you’ve invoiced your client for more work than you’ve actually completed or incurred costs for. In other words, it represents getting paid ahead of your work schedule.

Here’s how it works: If you’re a concrete subcontractor on a $100,000 job and you bill 50% upfront ($50,000) but have only completed $30,000 worth of work, that $20,000 difference is your billings in excess of costs. You owe your client that work, and until you complete it, that $20,000 remains as a liability on your balance sheet.

For subcontractors, understanding billing in excess of costs is essential because it can be a strategic cash flow tool when used carefully. For example, when bidding on a job, you can be smart about how you structure your schedule of values (SOV)—breaking work down into more detailed line items that allow earlier billing. However, this strategy requires regular monitoring to ensure:

  • Your billing somewhat aligns with your actual percentage complete, and 
  • The remaining contract value will still cover your remaining costs.

The biggest risk of overbilling is thinking your margins look better than they are, simply because you’re collecting cash faster. Surety companies and lenders also scrutinize overbillings closely, as excessive amounts can signal poor project management or potential cash flow problems down the road.

With Siteline, you can easily track whether you’re billing in excess of your costs by pulling your month-to-month incurred costs and comparing them against your billing progress. This real-time visibility helps ensure you’re billing appropriately while maintaining realistic profitability expectations. If you’re interested in seeing for yourself, schedule a personalized demo of Siteline here.

Ready to end the fire drill and get paid faster?

Replace the spreadsheets and runarounds with Siteline, and see your invoice aging improve by at least 30%.
many forms with different layouts